Navodaya Vidyalaya Samiti
Ministry of Human Resource Development
Request for Qualification
Response
to the queries raised by Bidders at Pre-Qualification Conference held at the
NVS Main Office on
The pre-qualification conference for setting up of Three
Navodaya Vidyalaya on Public Private Partnership (PPP) Mode was held at NVS
Office,
|
S. N. |
Query |
Response |
|
|
1 |
Technical capacity: for demonstrating technical capacity
and experience (Technical Capacity) the Applicant shall over the past 5
(five) financial years preceding the application due date, have:
(i)
paid for, or
received payments for, construction
of Eligible Project(s); and/ or
(ii)
paid for
development of Eligible Project(s) in Category 1 and/or Category 2 and/or
Category 3 specified in Clause 3.2.1; and/ or
(iii)
collected and
appropriated revenues from Eligible Project(s) in Category 1 and/or Category
2 and/or Category 3 specified in Clause 3.2.1, such that the sum total of the above experience is more
than the “Threshold Technical Capability” as defined in Clause 3.5.2 We request the authority to consider the value of
executed /executing projects as a qualification criteria since a BOOT/BOO
Project implementation is divided into payment receipt in multiple
installments |
BOOT/BOO projects are already included in the categories.
The value of executed projects are being considered as
per the clause 2.2 & Clause 3.2 No changes in Criteria proposed. The Criteria shall be as
per the provisions of the RFQ |
|
|
2 |
In case the Applicant is a Consortium, each Member should
substantially satisfy the pre-qualification requirements to the extent
specified herein. We request the authority to consider in case
the applicant is a consortium, members should jointly satisfy the
prequalification requirements to the extent specified herein |
The request is already addressed in the RFQ. The clause
under discussion only requires a consortium member to have the minimum
qualification (if any) specified for individual members of the consortium No changes in Criteria proposed. The Criteria shall be as
per the provisions of the RFQ |
|
|
3 |
Generally the highest bidder shall be the selected
Bidders We request the Authority to give the definition of
Highest Bidder in detail |
The parameters would be further defined in the next
stage. At this stage, the definition is as per Clause 1.2.5
& Clause 2.7.2 (i) |
|
|
4 |
Subject to the provisions of Clause 2.2, the following
categories of experience would qualify as Technical Capacity and eligible
experience (the "Eligible
Experience") in relation to eligible projects as stipulated in Clauses
3.2.3 and 3.2.4 (the "Eligible
Projects")’ We request the Authority to clarify in which Category
the following projects would fall under: Education ICT projects across government schools which
involve computer lab infrastructure set up, Hardware supply, supply of
computer teacher and annual maintenance for three year to five years. These
projects are normally in BOO/BOOT model and vendor payments are divided in
multiple quarters/years |
Based on the descriptions provided in the RFQ, bidders
are expected to carry out their own due diligence. Hardware supply shall not be considered. |
|
|
5 |
Subject to the provisions of Clause 2.2, the following
categories of experience would qualify as Technical Capacity and eligible
experience (the "Eligible
Experience") in relation to eligible projects as stipulated in
Clauses 3.2.3 and 3.2.4 (the "Eligible
Projects")’ We request the Authority to clarify that education
software projects & services with multiple year of maintenance will be
considered in which category |
Same as Query No 4 Software development including those for educational
purposes shall not be considered |
|
|
6 |
The capital cost of the project should be more than Rs
13 crore. We request the authority to consider the projects of 1
crore and above in this particular category |
No changes in Criteria proposed. The Criteria shall be as
per the provisions of the RFQ |
|
|
7 |
However, payments/receipts of less than Rs 13 crore
shall not be reckoned as payments/receipts for eligible projects. We request the authority to consider that in this
category that the total value of the project should be minimum 13 crore As Government projects payment cycle is longer in nature
and hence receipt of payment should not become the criteria for eligibility |
No changes in Criteria proposed. The Criteria shall be as
per the provisions of the RFQ |
|
|
8 |
Applicant’s experience shall be measured and stated in
terms of a score (the "Experience
Score"). The Experience Score for an Eligible Project in a given
category would be the eligible payments and/or receipts specified in Clause
2.2.2 (A), divided by the factor presented in Table 3.2.6-A and then
multiplied by the applicable factor in Table 3.2.6-B below. In case the
Applicant has experience across different categories, the score for each category
would be computed as above and then aggregated to arrive at its Experience
Score. We request the authority to clarify experience score
calculation |
Illustration provided in Addendum 1 |
|
|
9 |
Technical capacity of the applicant We request the authority to consider the total value of
the project in the formats also |
No changes in Criteria proposed. The Criteria shall be as
per the provisions of the RFQ |
|
|
10 |
Revenue details of the private sector We request the authority to give details on how private
sector will get the revenue from the project |
The private sector will receive an annuity payment
towards capacity creation and another annual payment towards service
delivery. The payments may also have a performance linked component.
The payments are expected to be made quarterly. These descriptions are indicative in nature. The binding
details would be provided in the RFP. |
|
|
11 |
Total contract period – we request the authority to give
details on the total contract period of the project |
The contract period will be 15 years of operation and 2
years for construction. |
|
|
12 |
Clause 2 Development concept – Is there any assurance by
NVS to provide stated number of students |
The students would be inducted and taught by the NVS.
The private player is expected to create the infrastructure, maintain the
same, and provide services. The capacity payment is not based on number of students
while service payments are expected to be per student basis. Further details would be provided in the RFP. These descriptions are indicative in nature. The binding
details would be provided in the RFP. |
|
|
13 |
Role of private player – we request the authority to
clarify that if project includes supply of teachers also |
Supply of teachers is not envisaged as a part of this
project. The scope includes:
i.
Construction
and maintenance of assets (buildings, residential hostels, staff quarters,
mess facility, library, IT infrastructure etc)
ii.
Provisioning
of services including mess facility for the students, hostel facilities, gym
and sports training facilities, and music learning facilitates
iii.
Limited
educational services which include ICT facility for NVS students, digital
library, and video conferencing facilities |
|
|
14 |
Scope of work for private sector – we request the
authority that would NVS also fund the operating expenses as envisaged in the
scope of work which includes maintenance of project assets etc |
Same as Query No 10 |
|
|
15 |
The payment to the developer would be made based on the
performance in each of the Navodaya Vidyalaya by the NVS – we request the
Authority to provide details on payment mechanism in greater details |
Same as Query No 10 |
|
|
16 |
Scope of work for private sector – we request the
authority to provide the details on the after school hour activity allowed to
the private sector and revenue sharing if any with authority |
No commercial activity would be allowed. Please refer to the Addendum
2. |
|
|
17 |
|
NVS reserves the right to add or reduce the number of
sites until the last date of submission of response against the RFP. The maximum number of schools that may be allocated to
the private player and the mechanism for allocation of these schools shall be
detailed in the RFP. . |
|
|
18 |
Project Cost
•
What is the basis of calculation of Project cost?
•
Is construction cost calculated on CPWD rates? What cost
index has been used for this?
•
If construction phasing is expected to extend to Year 5,
has cost escalation till Year 5 been accounted for?
•
Is Site development on the entire area, or part of the
area? What is the Site utilization pattern?
•
In Site 1 & 3, the area differs by 10 acres, but the
cost only differs by Rs. 50 lakhs. What is the assumption behind this?
•
Will the NVS provide availability of power and water
up-to the project site. Who will bear the charges for applying for power and
water connections for the project(s)?
•
What kind of extra facilities are envisaged. For
example, swimming pool etc
•
Does the cost include Furniture & Equipment for the
School, Hostels & Staff quarters? |
CPWD norms have been taken for Project cost calculation.
The cost index has been taken as 149 (as of march 2011). The power & water required during construction would
be managed by the private developer. The developer is free to envisage extra facilities like
swimming pool. However, no extra payment would be made to the developer. The costs provided are indicative and the bidders are
required to make their own cost estimations. |
|
|
19 |
Technical capacity - The Technical capacity is not
completely compatible with the Scope of Work for the project, and therefore
doesn’t reflect the experience to complete the delivery of the project
•
Given that it’s a time bound project with quality as a
PPP parameter, Project Management Consultancy experience for developing
educational infrastructure should ideally be an integral part of technical
capacity.
•
Experience in Educational services should also be a part
of the technical capacity
•
Category 1 i.e. experience in providing manpower to
government agencies/ public
o
Please support this with more details i.e. what kind of
projects are covered under this?
o
Whether manpower trained and placed with public /
private enterprises would be included in Category 1
•
Category 2: Whether ICT projects (provision of hardware,
manpower and maintenance for a fixed period to government agencies, which
involves capital investment and recurring expenses over the period of the
project) would qualify in the 4 sub categories of PPP projects.
•
The scoring for the various categories is not
consistent. For example, Category 1 assumes a minimum of Rs.16.8 crs, whereas
Category 3 has assumed a minimum of Rs.82.35 crs as Revenues/payment to reach
the threshold of 70. What is the basis of calculation for fixing this? |
No changes in Criteria proposed. The Criteria shall be as
per the provisions of the RFQ Manpower trained and placed with public/private
enterprises would not be included in category 1 so long as they have been
placed for Project Management Consulting or as a part of Project Management
Unit. |
|
|
20 |
Scope of Work - Is it mandatory for the private sector
to take up all 3 parts? Or are Point ii and iii optional (Support and Limited
educational services)? |
Yes, all three parts are mandatory. |
|
|
21 |
Enrolment plan Is it mandatory to follow the mentioned
Enrolment Plan? Or can a more aggressive enrolment plan be planned, for
better utilization of infrastructure facilities? |
The students would be inducted and taught by the NVS. The private player has no role in teaching or selecting
of students. |
|
|
22 |
Student capacity
•
While Student strength is 560, the hostel capacity is
576.
•
Even if it is fully residential, hostel capacity is
extra for 16 students
•
Future Expansion dormitory of o.5 block with 2 warden
residences after Phase B
o
In which year is this planned?
o
Does private sector have to invest in this?
o
The hostel capacity is already extra. So will the
student strength be increased proportionately and therefore construction of
additional classrooms? |
The current design has been based on blocks and some
extra blocks have been kept to serve any variations in the number of boys and
girls from year to year. It is required to create these extra blocks. Further, the design should be modular such that if an
expansion is planned in the future, new modules (blocks) may be added with
minimal alterations. Any future expansion has been deleted from the score.
Please refer to
Addendum 3. |
|
|
23 |
Performance indicators - What are the performance
indicators on the basis of which the annuity payment will be made for
construction/maintenance and/or other services? |
The details would be provided at the RFP stage |
|
|
24 |
Use of Facility
•
It is mentioned that the developer would have the right
to utilize the facilities during off hours for commercial purposes. Does this
extend to any commercial activity such as renting of the space for commercial
events or running a business centre?
•
Will the developer be allowed to utilize the school
campus to offer other social services on commercial basis e.g. medical
check-up and treatment, play schooling etc
•
Can the developer run a second shift for private
students? |
Same as Query No 16 No second shift is allowed |
|
|
25 |
Payment of Annuity
•
What is the payment schedule for the annuity?
•
In case the private partner decides to build the
infrastructure of Phase A and B together, will the annuity payment still be
linked to the capital expenditure incurred by the Private partner as per the
phasing. |
Same as Query No 10. Construction of Phase A & B may be carried out
together provided:
(i)
The developer
maintains the assets to be constructed under Phase B without any additional
charge to the NVS
(ii)
The construction
linked payment would be made as per the construction phasing envisaged by
NVS. |
|
|
26 |
Innovative design The RFQ “highlights” pictures of some private schools in
|
There are no pictures in the uploaded RFQ. |
|
|
27 |
Formation of SPV
•
Is formation of SPV mandatory for a single entity and
consortium?
•
If yes, Can the private partner use the SPV for other
related business?
•
Can this be made optional? |
We have taken a note of it. Suitable guidelines would be
provided at the RFP stage. |
|
|
28 |
Area of School plots |
Please refer to
Addendum 4 |
|
|
29 |
Elaborate on Manpower/Facility management – Will |
Manpower trained and placed with public/private
enterprises would be included in category 1 so long as they have been placed
not for Project Management Consulting or as a part of project management unit
but as a part of provisioning of long term services including maintenance
(for one or more years of operation). |
|
|
30 |
Can two phases of construction be carried out together |
Construction of Phase A & B may be carried out
together provided:
(i)
The developer
maintains the assets to be constructed under Phase B without any additional
charge to the NVS
(ii)
The construction
linked payment would be made as per the construction phasing envisaged by
NVS. This description is indicative in nature. Further details
will be provided at the RFP stage. |
|
|
31 |
Extension of Date |
The date of submission has been extended to Please refer to
Addendum
5 for details. |